[1.35.0] Progress report

In another thread, John Maddock wrote:
Where are we with the release process?
Our build and test infrastructure finally seems stable, and able to support the 1.35.0 release. Tests don't look too awful on our high-priority release targets (and I've just updated the list of high-priority targets so that the Unresolved Issues report reflects those priorities.) The inspection report is still shows an uncomfortably large number of problems, and I'm about to turn on more of the checks. Merging of libraries into branches/release is finally underway. Quite a bit of work has been done on the website. There are still lots of outstanding tickets. No attempt has been made yet to try to put the pieces together to shakedown the build release candidate process. I realize that from the perspective of not shipping a release until all but the most trivial issue are resolved, the above report seems overly optimistic. But I'm assuming we are committed to getting a release out sometime in December, and that it is better to get releases out regularly than holding releases until they are perfect.
Do we have some kind of schedule / deadlines for being ready to ship...
* Merge for release complete: Sunday, November 25th. * Start testing release candidate build process: Monday, December 3rd. * Release Candidate 1: Monday, December 10th. That implies clearing most of the remaining high-priority platform test failures in the next two weeks. --Beman
participants (1)
-
Beman Dawes