Hi, For each bug, there are really two levels of "fixed": roughly speaking, the developer considers the issue fixed when it is committed to trunk, while the user considers the issue fixed when it is commited to the release branch. At present, the trac ticket is closed at the first gate. Unfortunately, sometimes the second gate gets forgotten. Could another state be added to the ticket lifecycle to track when it gets merged to release? My aim is to be able to identified "fixed" tickets that are not actually released and, hopefully, to decrease them in number. Maybe there are other ways to achieve this? Regards, -Steve